***UPDATE 11/07/26***
Due to unforeseen circumstances, this portion of the project has been delayed by one week. As a result, all subsequent timelines associated with this portion of the project have shifted one week later.
Please refer to the updated schedule image below for the revised dates.
As our construction project progresses, upcoming underground utility work will require temporary adjustments to drop-off, pick-up, and pedestrian and bus lane traffic over the next few weeks. Thank you in advance for your patience and flexibility as we complete this portion of the project.
What We Are Building
You may have noticed excavation just west of the track. Crews are installing an underground storm-water retention system designed to capture and control rainwater runoff, preventing strain on the area's main drainage system. Once installation is complete, the structure will be fully buried and the ground will be leveled and restored.
Traffic & Path Shifts
Connecting this new retention system requires laying infrastructure along and across the current bus lane.
While most of this work will only require minor path shifts, the bus lane will be fully closed for approximately one week during the final connection phase.
Phased Construction Schedule
(Please refer to the site map for visual reference. Each stage is approximately one (1) week)
Stage 1 (Yellow) – Retention Area: Utilities will be laid from the retention area (west of the track) toward the bus lane. No impacts to traffic or walkways.
Stage 2 (Orange) – Temporary Path Shift: Work moves along the edge of the bus lane. Both the bus lane and pedestrian walkway will shift around the work zone. Additional staff will be present to help direct traffic.
Stage 3 (Red) – Temporary Bus Lane Closure: Crews will lay infrastructure across the bus lane, requiring a full one-week closure of the bus lane.
Relocated Bus Drop-Off & Pick-Up: All bus drop-off and pick-up operations will temporarily move to the east side of the building, in front of the elementary school.
The shift in pedestrian walkway will remain open during this phase.
Detailed Guidance Coming Soon: Specific drop-off routes, timing, and information on traffic flow for Stage 3 will be shared in a detailed follow-up message before this phase begins.
If you have any questions, please contact the Ridgeview District Office.